VLC Energy has become the latest firm to finish its Enhanced Frequency Response (EFR) battery projects following the completion of two projects totalling 50MW.
The joint venture, made up of VPI Immingham and Low Carbon which was the only tender winner in August 2016 to win two EFR contracts with National Grid, announced the completion of the projects alongside system integrator NEC Energy Solutions which commissioned the projects.
The 40MW battery park in Glassenbury in Kent and the 10MW battery park located at Cleator in Cumbria will deliver a quarter of the 200MW capacity secured by National Grid to provide sub-second grid flexibility to increase reliance on low-carbon forms of electricity generation.
Both the Cleator and Glassenbury sites have been awarded capacity market contracts in a leading example of how project revenues can be used over the lifetime of the project to provide a more secure income
Roy Bedlow, chief executive of Low Carbon, said: “These battery parks represent perhaps the greatest increase in UK energy storage capacity to date as part of National Grid’s EFR auction. We’re delighted to have developed these sites with our partners at VPI Immingham, and look forward to expanding VLC Energy’s storage portfolio.
“Energy storage is critical to managing the demands on the grid, ensuring consumer needs are met, and increasing our reliance on low-carbon forms of electricity generation. These sites will help us tackle climate change and help the UK realise a cleaner and more energy efficient future.”
The two sites, which have now been connected, use LG Chem lithium-ion battery modules and advanced energy management systems from NEC to respond to surges in energy supply and demand under the four-year contract.
The company was also contracted to operate the sites to provide the EFR service directly to National Grid on behalf of VLC Energy. This will be handled by part of the AEROS controls system using an automated operating mode designed specifically for the UK frequency response service.
The completion of the projects makes the Glassenbury and Cleator batteries the second and third projects supported by an EFR contract to be finished after E.On commissioned the 10MW Blackburn Meadows battery in September 2017.
The remaining five projects, to be delivered by Vattenfall, Foresight, Enel and EDF, will need to be completed by the end of February to fall in line with the demands of the EFR contracts.
While National Grid will now move away from a dedicated EFR tendering system to one that is expected to incorporate firm frequency response needs of the system. On the back of the success of battery technology in the first EFR tender, National Grid expects this form of storage to continue to play a role in maintaining the system while providing value for UK consumers.
Leon Walker, quantitative analysis manager at National Grid, said: “Using battery storage is a significant development for managing the national grid. It’s an ultra-fast way of keeping electricity supply and demand balanced.
“Over four years we estimate that this service will save the system operator around £200 million. This is good news for consumers who benefit from our cost efficiencies, and paves the way for battery technology to establish itself as an important component of our energy system.”
“Batteries hold the key to the future of the power landscape, both in the UK and internationally. Ensuring grid resilience is a necessary step in the growth of renewable generation,” added Russell Hardy, chairman of VPI Immingham and chief executive of EMEA at parent company Vitol.