National Grid’s T-4 auction for the 2021/22 winter period has cleared at a record low price as battery storage projects seemingly struggled to compete.
A total of 50.4GW of capacity was procured at a clearing price of just £8.40/kW per year, a record low for the T-4 auction and nearly one-third of last year’s T-4 auction clearing price of £22.50.
That low clearing price has seemingly limited the amount of new build capacity brought forward in the auction. Of that 50.4GW, just 762MW comprises new build generators, equivalent to just 1.5%.
CCGTs have predictably picked up the largest share of awarded capacity. More than 23GW – roughly 46% – has been shared between 44 different units. Its nearest competing technology by capacity is nuclear with 16 generators sharing just shy of 8GW worth of capacity.
Battery storage meanwhile only won 153MW of contracts with both the low clearing price and new de-rating factors combining to make it more difficult for the technology to compete.
A total of 3.3GW of battery storage was prequalified for the T-4 auction, de-rated to 1.344GW to account for their duration. This means that just 11% of battery storage projects secured CM contracts in this auction.
A total of 23 batteries won capacity contracts, some of which have successfully procured contracts in both last week’s T-1 auction and 2016’s Enhanced Frequency Response tender.
Arenko has proven to be the big winner in the battery storage field with four of its battery storage projects winning 15-year contracts for a total of 73.559MW, roughly half of the total capacity won by batteries.
Other winners in the battery storage field include solar developers British Solar Renewables and Lightsource.
Demand side response operators procured 1.2GW of tendered capacity. Big names in the space like Limejump (36.2MW), Enernoc (287.4MW), Endeco – now known as Gridbeyond – (114.2MW), Flexitricity (214.6MW) and Kiwi Power (276MW) were all successful, alongside utilities E.on, EDF and Npower.
Interestingly, interconnectors have increased their stake in the T-4 auction to take just over 9% of procured capacity, equivalent to around 4.5GW, 2.15GW of which is new interconnection capacity.
Those results mean that interconnectors, some from continental Europe, look set to play an increasingly important role in providing security of supply in the coming years against a backdrop of uncertainty over the UK’s future participation in the single electricity market (SEM).
The UK’s future energy relationship with Europe has proven to be a particularly contentious issue, with prominent bodies like the House of Lords and the Committee on Climate Change warning against both the effects of a botched Brexit and what it may mean for energy imports.
Meanwhile, coal has continued to witness its influence decline. Just 3GW of coal/biomass firing capacity was procured in this week’s auction with 7.6GW of capacity having exited.
Jonathan Marshall, energy analyst at the Energy and Climate Intelligence Unit, said coal was slipping off the “capacity market life support system… at long last”.
“This year’s auction shows that there is clearly more than enough capacity on the grid, and that we can keep the lights on even without resorting to the oldest and most toxic form of power generation.
“This takes us to four auctions without significant new large gas plants coming to fruition, which was once thought to be needed as a bridge towards a low-carbon power system. Utilities and lobbyists claim that these are needed for the future, yet legal carbon restrictions show they will face limited running hours into the 2020s and likely end up funnelling losses onto balance sheets – even if they could pick up capacity payments.
“Big gas plants are not needed to bridge the gap between coal and renewables, especially in the light of unprecedented falls in the cost of wind and solar power, which will lead to lower bills for homes and businesses going forwards,” he said.